27 Sep 2023 (Wed): Climate-Friendly Agribusiness Value Chains Sector Project (CFAVC), Midterm Review Mission conducted Field visit to Chum Kiri District, Kampot Province and Tramkak District,

27 Sep 2023 (Wed): Climate-Friendly Agribusiness Value Chains Sector Project (CFAVC), Midterm Review Mission conducted Field visit to Chum Kiri District, Kampot Province and Field visit to Tramkak District, Takeo province

I.          Commune: Chress, Chum Kiri District, Kampot Province

­     MAFF subproject: AC (batch II):

o   Lot 1: CW-b1/CFAVC/MAFF/2022-01 Construction of 5 ACs (in Kampot province); AC name: Raksmey Samaky Amatak Agricultural Cooperative completed (by KBH contractor completed date: 2 April 2023).

o   Meet with the AC member and management team on the roles of women in AC management and leadership (Gender).

­     MRD subprojects (Batch I):

o   Road ID: CW17a-CFAVC-MRD-KP-01-2020 (lot 1) Rural Road improvement (DBST); Road name: from Rovieng - Chres; Road length 11.94 km (by Royal Mekong Construction & Development Pte. Ltd contractor) physical construction progress at 54% (Contract completion date 3 March 2024).

o   Ms. Indah Social safeguard ADB proposed: DRP (Cat B) implementation docs (Completed /ongoing)

II.        Commune: Srae Khnong, Chum Kiri District, Kampot Province

­     MOWRAM subprojects 4-Subproject ID: CFAVC MOWRAM-KPT-CW12-1 Rehabilitation Irrigation scheme;

o   Subproject name: Takoch Reservoir Scheme (by KBH contractor, physical construction progress at 99%, contract completed date: (to be confirmed from MOWRAM).

o   Ponds construction.

o   FWUC formation.

o   Laser Land Leveling (MAFF)

o   Ms. Indah Social safeguard ADB proposed: DDR (Cat C) implementation docs (Completed /ongoing) for Takoch Reservoir Scheme, DDR approved by ADB week4, Dec 2022 (involvement of donation and verification).

­     MAFF subproject: AC (batch I)

o   Lot1: CW3a/CFAVC/MAFF/2021/04 Construction of 5 ACs (in Kampot province); AC name: Kasekor Samaki

o   Rung Roeung Agricultural Cooperative completed (by Huot Chhoeun contractor completed date: 27 September 2022).

o   Visit 2 rice seed demonstration productions, the Phkar Romdul (PRD) seed variety.

o   Meet with the AC member and management team on the roles of women in AC management and leadership (Gender).

­     MRD subprojects (Batch I)

o   Road ID: CW17a-CFAVC-MRD-KP-02-2020 Rural Road improvement (DBST); Road name: from Kamnab to Srae Chaeng; Road length 8.10 km (by Royal Mekong Construction & Development Pte. Ltd contractor) physical construction progress at 95% (Contract completion date 3 March 2024).

o   Ms. Indah Social safeguard ADB proposed: DRP (Cat B) implementation docs (Completed /ongoing)

III.      Commune: Trapeang Kranhoung, Tramkak District, Takeo province

­     MOWRAM subprojects

o   Subproject ID: CFAVC MOWRAM-TEO-CW15.1 Rehabilitation Irrigation scheme; Subproject name: Prey Kdoch Reservoir Scheme (by KBH contractor completed date: 5 May 2023.

o   Subproject ID: CFAVC MOWRAM-TEO-CW15.1 Rehabilitation Irrigation scheme; Subproject name: Kraing Empil Reservoir Scheme (by KBH contractor completed date: 5 May 2023 (to be confirmed from MOWRAM).

o   Ponds construction: (to be confirmed from MOWRAM).

o   FWUC formation: (to be confirmed from MOWRAM).

o   Laser Land Leveling

o   Ms. Indah Social safeguard ADB proposed: DRP (Cat C) implementation docs (Completed /ongoing) for Prey Khdouch and Kraing Ampil subprojects, DDR approved by ADB in week4, Dec 2022 (involvement of donation and verification).