On 27 Sep 2021, the same day, the third visit to Monitor AC's storage construction at AC-Ponlork Thmei, in Kangmeas District, KPC
On 27 Sep 2021, the same day, the third visit was then made to Ponlork Thmei AC, there is no construction work progress at this AC site so far. And the reason is due to waiting for the clarification of the design road width and the direction of road width expansion, which is not clear. The land plot where the warehouse is planned is at the corner of two existing roads. A long each road there is a borrow pit, from which soil was excavated and sold out in the area. The AC said that according to the commune Chief, these two borrow pits along the two corner roads are not the irrigation canals, belonging to PDWRAM, they could be back filled for road expansion. At this time final setting, out of the warehouse could not be done, because it is awaiting getting confirmation from the CS5 road design team, whether the design road expansion will extend from the existing right of way both sides (one side into the warehouse and another side into the borrow pit). The CS5 road design team was consulted and according to them, the design of this road section is required doing clarification with the AC members and the commune councils for the right of way availability.