On 27 Sep 2021, the same day, visit was then made to Monitor the progress of AC's storage construction of Aphivat Srok Yoeung
On 27 Sep 2021, the same day, second
visit was then made to Aphivat Srok Yoeung AC, which is located in Trappaing Thaut
village, Soksen commune, Beung Prey district, KPC. Over there, construction
works are progressed with its pictures as following:
·
Foundation
excavations for all the 11 footings were done with lean concrete casting and
brick formworks are in progressed. There is no other activity progress yet.
· Construction materials were brought to site such as stone aggregates, cement, sand and rebars.